They started the building this week. The first day they had a hydraulic hose break on the bobcat so they didn’t get much done. The second day they put the posts in the ground.
The third day they set the post and rafters.
Friday they installed the windows, but one they put in the wrong place. They will move it on Monday.
It so exciting to see this project moving ahead. There will be lots of work for us to do inside, but I’m looking forward to it.
Here is the progress they made on Monday.
Mattie always knows when I’m going to take a picture. She tries to be a part of it. |
Here’s the latest on the building. We are waiting for the plumber who said it would be at least 3 weeks before he could come. We also have a call into the electrician. After they are done, then we can call someone to come in and lay cement. Pat Welsh stopped by one day and said he didn’t like the way some things were done on the buildings so he is making them redo some parts. It’s always great to know the owner of the company:)